Future Ronaldsway ATC
Air Traffic Control developments at Ronaldsway
With the new control tower project well under way, a photo essay showing progress
towards an operational date in 2010
 
Island Images
IOM ATC Index
 
19th August 2008 - Just a grassy section section of the airfield! 
 
24th October 2008 - Groundwork has started on the site 
 
22nd November 2008 - More groundwork in progress 
 
18th December 2008 - First signs of vertical construction 
 
6th January 2009 - About to start work on the vertical 'stalk' construction 
 
12th January 2009 - An amazing difference six days later! 
 
13th January 2009 - Starting to rise above the skyline 
 
16th January 2009 - Still growing! 
 
17th January 2009 - and growing! 
 
21st January 2009 - Construction of the stalk almost completed 
 
2 February 2009 - Basic stalk construction finished 
 
9 February - The old and new towers from the runway intersection 
 
17 February - Brackets in place to support the two floors on top of the stalk 
 
21 February - A view of the airfield side of the stalk 
 
25 March - Concrete construction of the stalk completed 
 
4 April - Scaffolding erection to enable construction of the sub-cab area 
 
21 April - The Scaffolding continues to grow 
 
25 April - An early morning view 
 
11 & 12 May - Construction of the tower cab and lower building 
 
19th May - The lower building takes shape 
 
10th July - The Visual Control Room structure almost complete 
 
14th & 19th July - Glazing installed in the Visual Control Room 
 
23rd July - Views from the top! A visit to the new Visual Control Room 
 
17th & 26 August - the new VCR emerges 
 
27 October - 10th November - Scaffolding removed 
 
22 November - Two late afternon views 
 
January 2010 - External works all but complete
 